The 7 Stages of a Metal Building Order: From Quote to Install Day

The 7 Stages of a Metal Building Order: From Quote to Install Day

●  Quick Answer

A prefab metal building order typically takes 4 to 8 weeks from quote to installed building, moving through 7 predictable stages: design and quote (1 to 3 days), order confirmation and deposit (same day), engineering and drawing approval (1 to 2 weeks), permit submission (varies by county), steel manufacturing and quality control (2 to 4 weeks), delivery scheduling (1 week before install), and on-site installation (1 to 7 days). Starting permits early and approving drawings quickly are the two biggest timeline savers.

Get a Free Metal Building Quote  →

Ordering a prefab metal building for the first time can feel like a black box. You get a quote, pay a deposit, then wait. What actually happens during those weeks? Who does what? When should you prepare the site? What can delay the order?

This guide walks through all 7 stages of the metal building order process, in order, with realistic timelines and clear roles for both you and Bulldog Steel Structures. If you follow it from start to finish, your metal building arrives on time, your site is ready, and nothing surprises you along the way.

The 7 Stages at a Glance

StageWhat HappensTypical Timeline
1. Design and QuoteSpecifications locked, written quote issued1 to 3 days
2. Order Confirmation and DepositPayment method chosen, deposit processedSame day
3. Engineering and Drawing ApprovalDrawings built, customer signs off1 to 2 weeks
4. Permit SubmissionDrawings submitted to local building departmentVaries by county
5. Steel Manufacturing and QCFraming cut, panels formed, final inspection2 to 4 weeks
6. Delivery SchedulingInstall crew assigned, delivery date confirmed1 week before install
7. On-Site InstallationBuilding delivered, assembled, final sign-off1 to 7 days

Understanding each stage is the single best way to avoid delays and keep your project on track.

Gray vertical-roof prefab metal building with an enclosed storage room and open carport bay on a gravel pad

Stage 1: Design and Quote

Every prefab metal building order starts with a conversation about what you need. This is the stage where you lock in dimensions, roof style, framing gauge, doors, windows, colors, and any customizations. The decisions you make here flow through every other stage, so getting them right matters.

What Happens

You contact Bulldog Steel Structures through the website quote form, the 3D Estimator, or by phone. A building specialist walks you through your options based on your intended use (workshop, garage, barn, warehouse, carport, etc.), your location, and your budget. The specialist then produces a written quote with specific pricing and included features.

What You Need to Decide

  • Dimensions: Width, length, and eave height
  • Roof style: Regular, boxed eave, or vertical
  • Framing gauge: 14-gauge standard or 12-gauge upgrade
  • Enclosure: Open-sided, partially enclosed, or fully enclosed
  • Doors and windows: Sizes, quantities, and placement
  • Insulation: Type and coverage
  • Colors: Roof, walls, trim, and wainscot
  • Foundation plan: Concrete, asphalt, or gravel

Typical Timeline

1 to 3 days from first contact to written quote. If you use the 3D Estimator, you can see pricing in real time without waiting for a specialist to call back.

Tips to Speed This Stage Up

  • Build your configuration in the 3D Estimator before calling
  • Have your ZIP code ready for freight and local code pricing
  • Know your foundation plan (concrete, asphalt, or gravel)
  • Confirm your intended payment method ahead of the call

 

Lock In Your Specs Today.

Size, roof style, doors, colours and insulation, quoted for your site.

 

Stage 2: Order Confirmation and Deposit

Once the quote is accepted, your order moves into the production queue. This is where you choose how you’re paying and lock the build.

What Happens

You review and sign the final order document, confirming all dimensions, specifications, and the total installed price. You then choose your payment method and submit the required deposit.

Payment Options for Prefab Metal Buildings

Payment OptionDeposit RequiredBest For
Buy Outright10 to 50% deposit, balance on deliveryLowest total cost
FinancingVaries by lenderQualified buyers wanting long terms
Rent-to-Own Metal BuildingsFirst month’s paymentNo credit check, monthly payments
In-House Financing10 to 20% deposit0% interest first 6 months

Why Rent-to-Own Changes the Timeline Here

Rent-to-own metal buildings are the fastest path for buyers who want immediate delivery without the upfront payment typically required. Because there is no credit check and no application processing wait, the deposit stage moves from days to hours.

Typical Timeline

Same day in most cases. The deposit confirmation triggers the next stage.

What Happens If You Need to Change Specs

Changes made during Stage 2 are easy and often free. Changes made after Stage 3 (engineering) typically trigger change orders with additional cost and timeline impact. Lock your specs here if at all possible.

Also Read: Are Commercial Metal Garages Suitable for Auto Shops and Repair Centers?

Stage 3: Engineering and Drawing Approval

This is the stage most buyers do not see, but it is where your prefab steel building actually becomes real on paper. Nothing is manufactured until the drawings are approved.

What Happens

Bulldog’s engineering team builds complete fabrication drawings for your specific building. These drawings include every structural member, panel dimension, door framing detail, anchor placement, and load calculation specific to your location’s wind and snow codes.

Once drawings are complete, you receive them for review and sign-off. This is your final opportunity to catch any specification errors before manufacturing begins.

What to Check on Your Drawings

  • Overall dimensions match your order exactly
  • Door and window sizes and placement match what you want
  • Roof style and pitch are correct
  • Color selections are noted correctly
  • Eave height matches your specification
  • Any custom features (lean-tos, mezzanines) are included
  • Anchoring and foundation details match your foundation type

Certified Drawings for Permits

If your area requires engineer-certified plans (common for commercial use, high wind/snow regions, and some residential), the certification is handled here. Request certification at order to avoid delays and typically save money versus adding it later.

Typical Timeline

1 to 2 weeks for standard builds. 2 to 4 weeks for custom or heavily engineered builds. Certified drawings may add 1 to 2 weeks depending on your state.

What Delays This Stage

  • Delayed drawing approval by the customer (biggest cause)
  • Unusual spans or stepped roof configurations
  • Specification errors caught during review
  • Multiple rounds of change requests

Stage 4: Permit Submission

Permits are your responsibility, not Bulldog’s. However, this stage happens in parallel with Stage 3, so starting it early is critical.

What Happens

You submit the engineered drawings from Stage 3 to your local building department along with the required permit application and fees. The building department reviews the drawings for code compliance, zoning compliance, and setback requirements. Once approved, you receive your permit.

What to Confirm With Your Local Building Department

  • Current wind speed rating and snow load requirement
  • Minimum setback distances from property lines, roads, and structures
  • Zoning compliance for your intended use
  • Whether engineer-certified plans are required
  • Permit fees and payment method
  • Expected review timeline

Rural and Agricultural Exceptions

Some rural counties waive permits for agricultural-use buildings on qualifying acreage. Confirm this with your building department in writing before skipping the permit process. Even on agricultural property, enclosed structures typically still require permits.

Typical Timeline

Varies dramatically by county. Fast counties approve permits in 1 to 2 weeks. Slower counties can take 4 to 8 weeks or more. Call your building department early to understand their timeline, and start the permit process the day you place your order.

What Delays Permits

  • Missing engineered drawings
  • Setback or zoning violations requiring variances
  • Incomplete application paperwork
  • Backlogged building department
  • Required additional inspections (septic, environmental)

Stage 5: Steel Manufacturing and Quality Control

With drawings approved and permits in motion, your prefab steel building moves into actual production. This is where the raw galvanized steel becomes your building.

What Happens Inside the Factory

The manufacturing facility pulls your drawings from the production queue and starts fabrication:

  • Steel sourcing: Galvanized coil ordered to the exact gauges your drawings specify
  • Framing cutting: Vertical columns, roof trusses, and rafters cut to length
  • Precision drilling: Bolt holes drilled at exact engineered positions
  • Panel forming: Roof and wall panels roll-formed to your dimensions
  • Trim fabrication: All corner trim, ridge caps, and gable trim cut and shaped
  • Color coating: Panels and trim coated in your selected colors
  • Door and window fabrication: Roll-up doors, walk-in doors, and windows prepared

Quality Control Checkpoints

Before anything leaves the factory, your high-quality steel structure goes through multiple quality control checks:

  • Dimensional accuracy (every piece measured)
  • Coating thickness verification
  • Panel bend and seal integrity
  • Framing weld inspections
  • Hardware completeness
  • Load-rated anchoring hardware match

Typical Timeline

2 to 4 weeks depending on current manufacturing queue, custom specifications, and your location. Peak season (spring and fall) sometimes extends this to 4 to 6 weeks.

Why This Stage Cannot Be Rushed

Prefab metal building prices stay competitive partly because manufacturing runs on scheduled queues. Jumping the queue requires expedite fees and often is not possible at all. Plan your project around the manufacturing timeline rather than trying to accelerate it.

Stage 6: Delivery Scheduling

With manufacturing complete, your building is bundled, loaded, and scheduled for freight to your site. This stage requires coordination between the factory, the install crew, and you.

What Happens

Bulldog’s logistics team contacts you to confirm your delivery window. They coordinate with the install crew assigned to your region, confirm site access for the delivery truck, and set the actual install start date.

What Bulldog Confirms With You

  • Site access: Can the delivery truck reach your site?
  • Foundation ready date: Is concrete cured or gravel pad complete?
  • Permit status: Is your building permit approved and posted?
  • Install day availability: Will you or someone be reachable during install?

What You Must Have Done By Now

  • Foundation complete and cured (typically 7+ days for concrete)
  • Site cleared of obstructions
  • Vehicle access to site confirmed
  • Utilities marked if required
  • Permit posted at site per local requirements

Typical Timeline

1 week before install day for most deliveries. Bulldog contacts you to confirm the specific date and window.

What Can Delay Delivery

  • Foundation not ready
  • Site access blocked (snow, mud, construction)
  • Permit not posted
  • Weather forecast too severe for safe installation
  • Customer requested delay

Stage 7: On-Site Installation

The final stage. Your building arrives, the crew installs it, and your project is complete.

What Happens on Install Day

The Bulldog install crew arrives at your site with the complete building package: pre-cut framing, formed panels, hardware, anchors, doors, and windows. The install sequence follows a predictable order:

  1. Base rails anchored to your foundation
  2. Vertical frames erected and connected to base rails
  3. Roof trusses installed and secured
  4. Roof panels installed first, then wall panels
  5. Doors and windows installed in pre-cut openings
  6. Trim installed to finish all edges and corners
  7. Final anchor check and cleanup
  8. Walk-through with crew lead for customer sign-off

Installation Timelines by Building Size

Building SizeInstallation Time
Small (12x20 to 24x30)1 to 2 days
Mid-range (30x40 to 30x50)2 to 3 days
Large residential (40x60)3 to 4 days
Commercial (50x80+)4 to 7 days
Clear span 100 ft+5 to 10 days

What You Need to Do on Install Day

  • Be reachable by phone for any site decisions
  • Confirm final door, window, and extras placement
  • Keep pets, children, and other vehicles clear of the installation zone
  • Have water and basic cleanup supplies on hand
  • Inspect the finished building with the crew lead before signing off

What Happens After Installation

Final payment is processed per your payment agreement. Your warranty becomes active (typically 20-year rust-through on steel, 1-year workmanship). You receive your warranty documents and installation sign-off paperwork.

 

Get a Free Metal Building Quote.

See your price and a realistic install window for your location.

 

Realistic Total Timeline from Quote to Finished Building

Combining all 7 stages, here is what a realistic project timeline looks like:

ScenarioTotal Timeline
Simple residential (12x20 to 24x30)4 to 6 weeks
Standard garage or workshop (30x40 to 40x60)5 to 8 weeks
Commercial or custom (60x100+)8 to 12 weeks
Large commercial clear span (100 ft+ wide)10 to 16 weeks

Permit delays can add 2 to 6 weeks on top of these timelines. Starting your permit application the day you place your order is the single best way to keep the timeline on track.

What You Can Do to Keep Your Project On Schedule

Delays almost always come from one of five sources. Avoid these and your prefab metal building order stays on timeline.

  • Review drawings fast. Sign off on Stage 3 drawings within 48 hours of receiving them. Delayed approval is the single biggest cause of project delays.
  • Start permits immediately. The day you place your order is the day to call your local building department. Do not wait for drawings to arrive.
  • Prepare the site early. Concrete needs 7 days minimum to cure. Have your foundation plan and contractor lined up before Stage 1 is complete.
  • Lock your specifications. Changes after Stage 3 trigger change orders, additional fees, and timeline extensions.
  • Confirm site access. Make sure the delivery truck can physically reach your site. Low-hanging branches, soft ground, and narrow driveways cause installation delays.

Rent-to-Own: The Fastest Path to a Prefab Metal Building

For buyers who want immediate delivery without the upfront payment typically required for commercial loans or large cash purchases, rent-to-own metal buildings are the fastest path from quote to install.

Why Rent-to-Own Accelerates the Process

  • No credit check means Stage 2 (deposit and confirmation) moves from days to hours
  • No application processing wait means you skip the financing approval timeline
  • Low first-month payment removes the budget constraint that often delays orders
  • Immediate delivery scheduling triggers as soon as the first payment clears
  • Full ownership at the end of the 24 to 48 month term

For many buyers at this price point, rent-to-own is not just the fastest path, it is also the only practical one.

Frequently Asked Questions About the Metal Building Order Process

How long does it take to get a prefab metal building?

Most prefab metal buildings are delivered and installed within 4 to 8 weeks from order placement. Smaller residential buildings (12x20 to 24x30) often arrive in 4 to 6 weeks. Larger commercial buildings and custom specifications typically take 8 to 12 weeks. Permit delays can add 2 to 6 weeks on top of these timelines depending on your local building department.

Can I change my order after I place it?

Yes, during Stages 1 and 2 (quote and deposit confirmation). After Stage 3 (engineering), changes trigger change orders with additional cost and timeline impact. Changes after manufacturing begins may not be possible. Lock your specifications before Stage 3 if at all possible.

What happens if my permit is denied?

If your permit is denied, work with your local building department to understand the reason. Common issues include setback violations, zoning conflicts, or missing documentation. Bulldog can provide additional engineered drawings or revisions to help clear permit issues. Your building order can pause during this process without penalty.

Do I need to be home for installation?

Not required, but strongly recommended. The install crew needs someone available to confirm final door and window placement, approve any site adjustments, and sign off on the finished building. If you cannot be present, designate someone with authority to make decisions on your behalf.

What is included in prefab metal building prices?

Bulldog prefab steel buildings include engineered drawings, galvanized steel framing, roof and wall panels, doors and windows per your specifications, trim, anchors, delivery, professional installation, and warranty coverage. Foundation work, permits, site preparation, electrical, and plumbing are typically customer-arranged separately.

Can I buy a prefab metal building with no credit check?

Yes. Rent-to-own metal buildings are available with no credit check, low monthly payments over 24 to 48 months, and no early payoff penalty. This is the most popular payment option for buyers who want immediate delivery without the upfront cost of outright purchase.

What foundation do I need for a prefab steel building?

Most prefab metal buildings install on concrete slabs, concrete piers, asphalt, or gravel pads. Concrete slabs are the most common choice for permanent buildings with vehicles or workshops. Gravel works for lighter-duty storage buildings. Foundation preparation is the customer’s responsibility and must be complete before installation day.

How long does the actual installation take?

Installation time depends on building size. Small buildings (20x20 to 24x30) install in 1 to 2 days. Mid-range buildings (30x40 to 30x50) take 2 to 3 days. Large commercial buildings (40x60+) take 3 to 7 days. Clear span buildings 100 feet wide or more may take 5 to 10 days.

What happens if the weather is bad on install day?

If weather is forecast to be unsafe for installation (heavy rain, snow, high winds, lightning), Bulldog’s logistics team will contact you to reschedule. Severe weather delays are rare but do happen. Weather delays typically push installation by 1 to 7 days.

Can I speed up my prefab metal building order?

Some stages can be accelerated. You can request expedited drawings (additional cost), approve drawings within hours of receipt, start permits the day you place your order, and prepare your foundation early. Manufacturing itself runs on a fixed queue and typically cannot be expedited except in rare cases with additional expedite fees.

The Bottom Line

A prefab metal building order moves through 7 predictable stages, and the timeline is almost entirely within your control if you understand what each stage requires. Review your drawings fast, start permits early, prepare your site on schedule, and lock your specifications before engineering begins. Follow this sequence and your high quality steel structure arrives on time, installs cleanly, and starts delivering value from day one.

The two biggest timeline savers are starting permits the day you place your order, and reviewing engineering drawings within 48 hours of receipt. Delays at either stage ripple through every stage that follows.

Ready to see what your prefab metal building would cost and when it could be installed?

Get a Free Metal Building Quote  →

Or contact our team to discuss custom specifications, rent-to-own metal buildings options, and realistic timelines for your location.

 

Get a Free Metal Building Quote.

Talk through size, payment options, permits and install timing with a specialist. Call 888-551-2156.

 

What Our Customers Are Saying

I'm really happy with the way my building turned out! Due to living in city limits I had to make changes to my original plan but working with Bryan made it easy. He was great to work with!

Corey Evans

Bulldog Steel Structures is fantastic. We had a 24'x40' garage built with two 10' garage doors, an entry door, two windows and fully insulated for under $16,000. The whole experience was so easy. Our salesman was Bryan Valadez. Bryan was so helpful and was easily available to answer my questions. Rebekah Aldridge handled all the documents and signing of them. The whole process was great. The building is well constructed and the crew that erected it were courteous and cleaned the worksite afterwords thoroughly. They did an excellent job in a time efficient period. Our experience with Bulldog Steel Structures was just great and we highly recommend them.

Mattie Roberts

I'm in early stages, just put deposit on building. I reviewed about 10 quotes and worked with many vendors in the space to assess. Constance from Bulldog Steel Structures made the experience fabulous and was key in our decision making. It's so refreshing to see a company like this have such outstanding client facing service. We are excited and huge shout out to Constance and the team. Bravo!

Max Escuder

I have purchased two structures/buildings from them and have been greatly satisfied. From "idea to implementation" it has gone smoothly. I love the idea of having one single point of contact (Noah) for any questions or concerns. The install crew comes in and gets right to work and the quality is the best I have seen. Highly Recommend!

Ron Barnes

I worked with Bryan Valadez in putting together my bids for a 2000 SF shop/garage. He was great to work with, very quick to respond and answered all my questions and concerns during several very thorough conversations regarding my project. I recommend you give Bulldog a shot when searching for your next building, their pricing was very good compared with some of the others, and they just seemed to have it very together for their process. Great Job, thanks Bryan. Jason

Jason Ford

Showed up on time and excellent quality. Could not be more pleased with the results!

Drew Hood

I called and spoke to Bryan. With some back and forth he helped me finalize the design (40x100 foot print). I placed my order and had to wait for my King County building permit to be issued. Once the slab was completed the installation team arrived with all the pieces. They got right to work and the building was completed in 8 days !!! I would highly recommend Bryan and Bulldog to any one :) Many thanks john in the pacific northwest

John Marcus

Great company to do business with. Would recommend them to others.

Webster Smith

Great to deal with. Building went up with no problems.

Florida Chapter POCI

I had a great experience with Bulldog Steel Buildings. The representatives were able to help me move from the online design to an actual building design to meet my goals. They set up the delivery and installation which turned out great. Installation was scheduled quickly after the foundation was done; and the building was completed within 2 days. Pricing was reasonable, and I'm very pleased with my new building.

David Grover

Bryan was great- honest, helpful, responsive and knowledgeable. I will call him if I ever need another steel building

Allan Brown

This company is the real deal. They go over and beyond to satisfy their customers. It is a joy to work with them. They are very knowledgeable and efficient. I looked forward to finishing my project with them.

David Thomas

Humberto was very responsive and it was a pleasure to work with. He went above and beyond to get delivery scheduled as soon as possible for our 30x50 building. Great company to work with.

Kelly Heckel

Hey folks - these people at Bulldog are real. Noah helped me all the way through - extremely patient and knowledgeable. He answers most often and when he doesn't it's easy to get another HUMAN to speak with. I looked at several companies for this project - I settled on the right one. If you wind up doing business with Brian - you're in luck there to. Outstanding work - worthy of trust.

Randall Drew

I purchased a 26x32 Garage from Bulldog Steel Structures they had it finished in two days. It looks really nice and the install crew was great. I’m thinking of getting another building and I will definitely contact Bryan Valadez again at Bulldog.

Kris Phillips

Great experience from start to finish. The sales process was easy and Casey helped me revise my plans several times to get the right building for my needs. Communication was excellent! The build crew was on time, friendly and professional. Beto took the time to understand what cutouts I needed and why I needed them in the sizes planned. Exceptional work. Highly recommend. Thank you!

Damon Trim

I would recommend Bulldog Steel Structures highly. They are very professional and accommodating. Want to give special thanks to Randall Hall and also matt preslar. They were very accommodating and helping me fill out paperwork and handling things when a timely basis. The building we were very satisfied with and the installers also were very polite and had things done on a timely basis. Thanks again Randall and Matt you`ve got my five star rating

Shirley M.

Bulldog has been great to work with. They explained everything from beginning to end. I live in the mountains of New Mexico and the staff made sure that my garage had the right support needed for this area of the country. I would highly recommend them for anyone building a new carport or gaeage!

Bruce J.

Good design tool on their website. Great customer service.

John S.

Have had nothing but a positive experience with Bulldog! Bryan was super helpful and still is after our install! He still responds super prompt and helpful. No complaints about our structure, as it looks amazing! Installers did a great job and picked up very nicely after they were done. Highly recommend!!

Kristie S.

I have now had my building in place for 3 months and I want to say that the whole team at Bulldog was very helpful throughout the entire process. My salesperson, Matthew, was extremely responsive. He was very helpful with the design phase, where we went back and forth with 3-4 different designs before settling on the perfect one. He always got back to me right away when I had a question. Although the delivery was delayed, understandable with the pandemic, he helped interface with Carolina Carports when I had delivery questions. So far I have no issues with the completed building. No leaks and all the doors are functioning perfectly. I would highly recommend using Bulldog for all your metal building needs.

Mike W.

Frank Rangel was very helpful and respectful. Also very understanding. I was pouring a concrete driveway and trying to put my down payment down. I may of got a little frustrated in the middle of it all. I could see the smile on Frank`s face the whole time! Thank you sir!

Jason M.

This is my second building from bulldog and I`m buying the same building , just different colors. They are great buildings that are strong and economical.

Parke H.

Excellent customer service during my order process, answered all my questions and they were very patient.

Jack D.

The website was very flexible and helped me customize my carport. The Bulldog staff was very prompt and helpful throughout the process.

Dale & Karen W.

Put up a RV cover for me on a concrete pad. Turned out great and the guys cleaned up after the work. Very satisfied. Would recommend these people.

Dan and Linda I.

I love my “She Shop.” It was amazingly easy. I sent an email, made 2 phones calls and it was done. The installation went even easier. Three guys showed up one day and finished the next. They were polite and cleaned up after themselves. My husband’s friends are all very impressed with the construction and materials used but were amazed at the reasonable price. I could not be more pleased. Thank you

DTheressa J.

I visited their website and used the 3D estimator and was able to see my building with doors, window placements, colors,and overall look. When you add or change any feature, including size, you can immediately see the result and change in price (if any). You can rotate the structure to see the overall look and framework. Once I placed my order, it was quickly and efficiently handled and the cost was lower than the estimate on the website The installers showed up early one morning and by noon the next day they had completed the structure. Everyone that comes by remarks on how nice it looks. I am very pleased with every aspect from ordering to installation.

David T.

Delivering & installing throughout the United States

Bulldog’s metal barns, garages, and carports are available for delivery and installation in most of the U.S. Whether you’re a homeowner in Maine, a rancher in Texas, or a small business owner in California, you’ll get to-your-door delivery and professional installation, so your building will be sturdy and reliable for years to come.

Background Texture
Ready to take the next step?

Talk to a Professional

Become part of thousands of satisfied customers who trust us to protect their investments.